How to write a statement of work for a museum exhibit RFP

You have to figure out what you need before asking consultants what it will cost.

Every exhibition consultant has opened a request for proposals (RFP), read it twice, and wondered whether the organization issuing it is anywhere near ready to pursue an exhibit planning process. 

Sometimes the answer is no. And that’s perfectly understandable. Knowing what you need is often the first—and most difficult—part of an exhibition project.

Before you draft your statement of work, sit down with your project sponsor, your project manager, and any other key people, and talk each other through these questions. Take detailed notes. Your answers will help you distinguish what you’ve already decided, what you need a consultant to investigate, and what constraints the project will need to accommodate.

1. Desired outcomes and deliverables

What do you hope to have when the funded assignment is finished? An interpretive plan? An exhibit concept with preliminary sketches that can support capital fundraising? A fully designed exhibit ready for tender? An installed exhibit?

2. Funding and schedule

Do you have a preliminary budget or budget range in mind? Is that based on previous project experience, professional estimates or simply the funding available? Or are you at an early planning stage, where consultant proposals will help you establish a realistic budget? Does your budget cover the entire project, or only the planning and design work?

What funding program are you pursuing, if any? Are there limits on eligible costs or deadlines that will affect the scope of work?

What’s your ideal completion date for this assignment? And what’s the absolute latest it could be finished? Are there other fixed milestones or deadlines that are outside of your control?

3. Extent of renewal

What is prompting this project? What is no longer working, or what new opportunities are you hoping to pursue? What problems will this solve?

Do you foresee a relatively straightforward refresh of an existing visitor experience, or a more substantial reconsideration of its purpose, interpretive approach and direction?

4. Content and research requirements

Are the stories, research, and collections already well established, or will the project require significant original research, interviews, collections work, development of new narratives, or obtaining permissions and clearing rights?

Are there particular cultural protocols, language requirements or sensitivities that will need to be addressed?

5. Existing plans and reports

Do you already have an interpretive plan, audience research, institutional strategy, content inventory, community engagement findings or other relevant studies?

Are these documents current, useful and generally supported within your organization?

6. Community and partner engagement

To what extent will your board, staff, community partners and other stakeholders need to be involved in developing the project?

Will the process involve consultation, collaborative planning, co-development or other forms of engagement?

Are there Indigenous Rights and Title Holders whose involvement and decision-making roles need to be established? What will their role be?

7. Governance, reviews and approvals

Who is championing the project? Is there internal consensus about its need and direction, or is it still an idea being explored within your organization?

Who will manage the project and who has authority to approve its direction and deliverables?

What review and approval processes do you anticipate? Will the work require formal community review, visitor testing, technical approvals or multiple rounds of feedback?

8. Physical space and uses

How large is the space or site? How is it currently used? How many different purposes or configurations does it accommodate (exhibitions, events, classrooms, workshops, etc.)?

Is the project confined to a particular gallery or building, or might it extend into outdoor spaces or other parts of the visitor experience?  What is the floor area, in square metres or square feet?

How exhibition-ready or experience-ready are those spaces? 

Will the space need to remain operational during the project?

9. Building and technical conditions

Are there known building deficiencies, conservation requirements, accessibility issues or planned capital improvements that might affect the project? Have relevant assessments been completed?

What HVAC, electrical, lighting, data and other technical infrastructure currently support the space?

Are there existing exhibits, furnishings, showcases, equipment or media that you expect to retain, adapt, relocate or remove?

10. Media and interactive complexity

What complexity of exhibits or visitor experiences are you envisioning?

Are you thinking primarily of graphics and objects, hands-on exhibits, audiovisual presentations, digital interactives, immersive environments or some combination?

11. Operational requirements

What operational conditions will the new visitor experience need to accommodate?

Think of staffing levels, visitor capacity, seasonal operations, security, maintenance (daily, weekly, monthly), accessibility or use by different audiences.

Are there requirements for bilingual or multilingual presentation, captioning, audio description or other accessible media?

12. Internal expertise and capacity

What relevant expertise and resources can your organization contribute to the project?

Do you have subject matter experts, curators, conservators, researchers, community engagement specialists or technical staff who can participate?

How much staff time could realistically be available for research, content development, coordination and reviews?

13. Location, logistics and implementation

Where is the project located, and what logistical considerations might affect the work?

How much on-site participation do you anticipate for workshops, consultation, research, design reviews or installation? What could reasonably be accomplished remotely?

If the project proceeds to implementation, do you expect a single consultant-led team to coordinate fabrication, procurement, installation and commissioning, or will some responsibilities be managed separately?

Are there procurement policies, contracting requirements or funding conditions that will affect how the project is structured or delivered?

14. Anything else?

Is there anything else a prospective consultant should know about your organization, site, aspirations, constraints or expectations that might influence the scope, cost or successful delivery of this project?

What if we don’t know the answers?

That’s perfectly okay. That’s why you’re doing this.

Let’s say you’re not sure whether you need a modest exhibition refresh or a fundamental rethink of your interpretive approach. Or perhaps there are differences of opinion within your organization.

That’s a valuable discovery. It could save you considerable time, money and heartache.

Rather than rushing ahead with an exhibition design RFP, consider whether you need to resolve those questions first. You might commission an interpretive plan as a separate assignment, or undertake the planning work in-house before moving into a larger contracting process.

The point isn’t that you need to have every answer before you hire a consultant. It’s that you need to understand which questions you’re hiring the consultant to answer.

Good planning is all about making the important decisions before you make the expensive decisions.


Hey does this kind of writing tickle your brain? Sign up for monthly goodness from donenright.com.

Wanna see what past newsletters look like? Clickity click.

Get monthly (ish) updates via email from Don Enright. I write about interpretation and visitor experience. I never sell or share my lists.

This field is required.

Comments

Leave a Reply

Your email address will not be published. Required fields are marked *

This site uses Akismet to reduce spam. Learn how your comment data is processed.